Following is a list of new sidewalk projects planned for the city. Work is expected to begin this year if weather permits. The combined projects total 1.2 miles.
• Jones Mill Road; North Side; Bay Colony-Jones Mill Spur; 3,000 linear feet
• Jones Mill Spur; North Side; Jones Mill Road-Peachtree Corners Circle; 400 linear feet
• Peachtree Corners Circle; North Side and South Side gap fill; Peachtree Industrial Boulevard
Southbound Access Road-Jones Mill Spur; 2,400 linear feet
• Engineering Drive; South Side; Existing sidewalk to S.R. 141 (Peachtree Parkway); 500 linear feet
For additional information on the city’s plans for road, sidewalk and intersections improvement projects:
- Visit the city’s website, peachtreecornersga.gov.
- Locate the “Government” tab.
- Select “Capital Improvement Projects” in the pull-down menu.
For any questions, please contact Public Works via email at publicworks@peachtreecornersga.gov or by
telephone, 678-691-1200.