Construction on the pedestrian bridge that will connect the Town Center and The Forum is currently on schedule. To complete the project, a portion of S.R. 141 (Peachtree Parkway) will be closed to traffic during the next two weekends.

During the closures, Medlock Bridge Road and Peachtree Corners Circle around the Town Center will be used as detours for both northbound and southbound traffic.

The schedule at this point, barring any weather delays, is for the first detour to take place at 9 p.m. Friday, June 5 through 5 a.m. Monday, June 8. The actual bridge span will be installed at this time.

The second detour will take place Friday, from 9 p.m. June 12 through 5 a.m. June 15. This time will be used to pour the bridge deck and install the pedestrian panels. Keep an eye out for public updates.

Source: City of Peachtree Corners peachtreecorners.gov