The City of Peachtree Corners is providing this information as a construction update for the Bush Road at Medlock Bridge Road project. The goal of this project is to improve the intersection of Medlock Bridge Road, Bush Road, and the slip ramp to State Road 141. The project is currently under construction.
This project includes the following:
- Two lanes added to northbound Medlock Bridge Road to accommodate a left turn lane
- Through lane leading to SR 141 South
- Through lane to East Jones Bridge Road
- Through and right turn lane leading to both Bush Road and the slip ramp leading to North SR 141
- Second right turn lane added to Bush Road that leads directly to the SR 141 slip ramp
- New traffic signal installed to aid in the operation of these new lanes
- Widening and traffic signal on Medlock Bridge Road and Bush Road
In addition, this project also includes a new concrete sidewalk, island, curb and gutter, asphalt paving, drainage improvements, modular block retaining wall, overhead signs, ornamental fence and ornamental trees.
Current Status of Project
Complete:
- Drainage improvements, retaining wall, and general grading
- Most concrete work
- Base layer asphalt for the Medlock Bridge Road and Bush Road turn lane extensions
Remaining:
- Overhead utility relocation
- Traffic signal installation
- SR 141 slip lane construction
- Concrete island and ADA ramp construction
- Final asphalt layer installation
- Guardrail, sod, decorative trees, ornamental fence, signing and marking
Remaining Schedule/Milestones (estimated):
- Georgia Power to set three joint-use poles and five utility poles – Mid December 2021
- Traffic Signal Installation – January 2022
- Overhead facilities relocated to new poles by Georgia Power, Comcast, AT&T, Zayo – February 2022
- Existing pole removal by Georgia Power – February 2022
- Guardrail, signs, fencing, trees, filling gaps in sidewalk, curb and gutter, sod, final asphalt paving and striping – March 2022